Progress Photos 30th June 2007
|
|

|
|
|

|
|
Installation of MV Switching Panels at SS4 |
|
|
|

|
|
SS4 MV Switching Panels Assembly Completed |
|
|
|

|
|
Cutting the Line 6 Kiln Shell for replacement |
|
|
|

|
|
Welding and Edge Preparation of New Kiln Shells |
|
|
|

|
|
|

|
|
Progress on Belt Conveyors replacement |
|
|
|

|
|
Installation of Distribution Transformers |
|
|
|

|
|
Limestone Covered Storage Yard Civil Works Progress |
|

Ducting Insulation work Started
|